OpenAINov 4, 2026 · 3 min read

OpenAI wants its AI data centers called "compute campuses"

As 73% of voters say no to one in their town. The new name, the power plan, and what it means for your bill

By Bots on Payroll, with 8 sources below

Sam Altman
Photo: Village Global, CC BY 2.0

The short version

  • Data centers have become a hard sell.

Watch the video

0:54, sound on

"Not gonna pay double"

Data centers have become a hard sell. In a Quinnipiac poll released Sept 29, 73% of registered voters said they'd oppose an AI data center in their own community, and only 21% would support one. That's up from 65% opposed in March. Quinnipiac's Tim Malloy put it simply: voters are saying not in my back yard.

Say "compute campus"

Axios reported on Nov 1 that OpenAI was preparing a campaign that includes a new name for its data centers. The phrase first showed up in OpenAI's Nov 2 announcement, where The Verge counted the words data center only twice in about 900. An OpenAI spokesperson told Business Insider that compute campuses better describes the scale of what it's building.

Power down when the grid is strained

Grid Protectors, announced Nov 2, makes future OpenAI campuses cut their power use when the local grid is under strain. The pilot is a planned 3.2 GW campus in Effingham County, Georgia. Under a 25 year deal, Georgia Power can cut up to 1,000 MW from the site at busy times, about the demand of 700,000 homes. OpenAI says no other sites are named yet.

Who pays for the power?

ABC News met a woman near Chicago whose power bill rose 23% in a year, with a data center 1,000 feet from her yard. In Port Washington, a $15 billion OpenAI and Oracle campus will use about as much power as every home in Philadelphia. OpenAI says it will pay for its own power lines, and Georgia Power expects deals like this to save customers about $950 million a year from 2029.

"It's a people issue"

The pushback crosses party lines. In the Quinnipiac poll, 85% of Democrats, 76% of independents and 55% of Republicans oppose a data center in their community. The Annenberg Public Policy Center found 61% opposed this summer, up from 49% in the spring. Bloomberg reports that groups aligned with Anthropic and OpenAI have put about $56 million into elections.

"Changing the name does not fix the problem"

Holly Elmore of PauseAI US says OpenAI is clearly responding to how unpopular data centers have become. Abre' Conner of the NAACP's climate justice center says changing the name does not fix the problem. OpenAI itself admits that cutting power at busy times can't replace building new power plants and power lines. Aurora, Illinois has already paused new data centers for 180 days.

Rivals promise to pay their way

OpenAI isn't alone. Anthropic pledged to cover all of its grid connection costs and to avoid nondisclosure agreements with local officials. The White House has asked builders to sign a voluntary pledge to cover their own power costs, and Google and Nvidia formed an alliance to make data centers flex their power. ABC counts about 1,200 more US data centers under construction or planned.

Swipe the post

Slide 1 of 9Slide 2 of 9Slide 3 of 9Slide 4 of 9Slide 5 of 9Slide 6 of 9Slide 7 of 9Slide 8 of 9Slide 9 of 9